Broad Philosophy and background. Features of the form. Changes from Second Edition. Documentation. Options and core clauses. NEC Contracts available. Partnering Option X12. Options Y(UK)2 and Y(UK)3. Other Secondary Options. Option Z. Risk Register.
Administration - Personalities and Approach
The role of Employer, Project Manager, Supervisor, Adjudicator and Contractor. Contract Data and Site information. Communications and early warning. Ambiguities and inconsistencies. Rights of Third Parties ± Y(UK)3.
Duties and Responsibilities - Contractor
Providing the Works. Co-operation. Access. Contractor design - Standards and obligations. Instructions. Quality of work. Testing, defects and correction. Key Performance Indicators Option X20. Low Performance Damages.
Time for Performance
Access. Starting date. Commencement. Status of the programme. Acceptance of programme. Order and time of work. Key Dates. Programme revision. Taking over. Acceleration. Sectional completion. Completion Date. Completion delay damages. Bonus for early completion.
Insurance and Damage
Damage to the Works, people or properly. Indemnities. Insurances.
Payment
Defined cost. Fee percentage ± Subcontract and direct. Work done to date and interim payment. Interest. Retention, title, cost components. Construction Act and Y(UK)2. Security. Advance Payment.
Compensation events
The events including quantities, mistakes, physical conditions and breach. Extension of time and financial compensation. Notification. Quotations/assessment. Implementing compensation events. Schedule of Cost components. Early warning. Interest. Additional Compensation Events.
Disputes and Termination
Adjudication and Y(UK)2. Options W1 and W2. The adjudicator and the procedure. The tribunal. Termination.
INTRODUCTION TO THE ENGINEERING AND CONSTRUCTION CONTRACT- THIRD EDITION
Background
The consultative document was published in 1991, the first edition in 1993, the Second Edition 1995 and the Third Edition in July 2005.
Many people believe the first edition was published in response to the Latham report. However the consultative document and first edition predated the report. The Latham report being published in 1994.
Latham identified the NEC (as it was then called) as being the contract which, more than any other in general circulation at the time, contained many of the provisions which Latham considered should be adopted in Construction Contracts. Out of the 13 key issues which Latham thought should be adopted, the NEC had 8. The full list of key issues from Latham is as follows:
The revision of the NEC and the publication of the Second Edition was in response to Latham and was intended to ensure that all 13 key issues were provided for.
Cont. ..../



